# Project Quiver — Phased Project Proposal: September to November 2026

- Space: [Arrow Air](https://snapshot.box/s:arrowair.eth.md)
- Author: 0x17C65468F4493B53E4e242A9671C91bbF445C1B9
- State: Passed
- Voting type: Basic
- Start: 2026-09-04 19:59 UTC
- End: 2026-09-11 19:59 UTC
- Votes: 6
- Quorum: 2,000,000 voting power
- Discussion: https://dao.arrowair.com/t/project-quiver-phased-project-proposal-september-to-november-2026/187
- Open in Snapshot: https://snapshot.box/#/s:arrowair.eth/proposal/0xb57e5dc5e9ef3e2d2b5515ca18ac65eece30dbaeeb22a22030077a6bd0aff4c7

## Results

- For: 3,023,486.89 voting power, 74.1%
- Against: 0 voting power, 0.0%
- Abstain: 1,054,836.68 voting power, 25.9%

## Proposal

# Project Quiver — Phased Project Proposal: September to November 2026

> Snapshot version. The full proposal with complete budget tables is on the [forum](https://dao.arrowair.com/t/project-quiver-phased-project-proposal-september-to-november-2026/187)

Project Quiver is moving from monthly funding requests to a phased project proposal, a format change agreed on the August 4 team call so the DAO can see where funds go against a roadmap rather than a rolling monthly ask. The Houston build concluded July with eleven flights across five sessions, including a 20.7 minute endurance record. August delivered the US meetup build week, where the team built and tested multiple working payload attachments, and closed with twelve flights across three field days opening the obstacle avoidance validation campaign. Full details are in the [July](https://dao.arrowair.com/t/182) and [August](https://dao.arrowair.com/t/project-quiver-august-2026-progress-report/185) progress reports.

This proposal also restructures how Quiver pays for work. The project moves from six monthly retainers to one retained lead plus a priced task board, cutting the monthly commitment burn 31% (from $8,760 to $6,000). July and August commitment grants are covered retroactively at the old rates. Remaining unassigned funds on the multisig consolidate into QGB-FLEX, the standing discretionary bucket, which now carries an operator onboarding fund, commercial readiness work, and an open task pool. The total treasury request is **$35,520 USDC**, 19% below what the outgoing structure would have asked for the same period. **No new $ARROW is requested.**

## Budget

| Category | Amount |
| --- | --- |
| Commitment grant back pay (July + August, six contributors, old rates) | $17,520 from treasury |
| Project Lead retainer (September to November, 20 hrs/week) | $18,000 from treasury |
| Task board | $18,786.83 already on the multisig ($10,150.00 honored commitments + $8,636.83 QGB-FLEX), no new ask |
| Retroactive grants (July + August) | 30,000 $ARROW allocation from held reserves, 12,750 distributed, no new ask |
| Retroactive grants (September to November) | Requested at the roadmap checkpoint and phase close |
| Flight Test Campaign | 10,000 $ARROW (carried from April, no new ask) |

**Total Treasury Request: $35,520 USDC**

## Compensation Restructure

From September 1, the Project Lead is the only retained contributor, 20 hours per week at $6,000 per month, covering flight operations, task board administration, documentation, treasury execution, and reporting. This holds the current hourly rate while doubling the committed time. A priced task board replaces the other five retainers. Tasks carry a price, an owner or open status, a deadline, and a definition of done, and pay on acceptance. Monthly retroactive $ARROW continues for contributions nobody assigned. The intent is to avoid retainers paying out regardless of output, to progress the bounties that sat unclaimed or stalled, and to keep the project lead from absorbing unassigned work by default.

No bounty allocation is redirected to payroll. Idle allocations (QGB-04 $3,000 and QGB-01 unassigned $3,480.21) consolidate into QGB-FLEX, which then holds $8,636.83: an operator onboarding fund ($1,500), commercial readiness work ($1,000), the Marketing Discovery line ($375), and $5,761.83 unassigned as the open task pool. The wind limit study returns at the checkpoint once its dataset exists. Honored bounty commitments (QGB-02 $4,000, QGB-05 $3,000, QGB-03 $600, and $2,550 of priced QGB-01 items) continue unchanged, and the multisig's $18,786.83 matches its obligations to the cent.

## Roadmap

| Phase | Window | Focus | Exit criteria |
|---|---|---|---|
| 1 | September | Flight validation | Avoidance enabled flight flown, GPS interference characterized and dual GPS restored, documentation backlog merged to GitHub, task board live, August retro distributed |
| 2 | October | Attachments | Attachment interface redesign decided and replacement ordered, first attachment flying on the interface, endurance study delivered |
| 3 | November | Product definition and operations scale | Product refinement scope adopted with a named owner, engineering report published, dev-kit pricing and reliability metrics published |

**Phase 1** closes the obstacle avoidance flight cards and the GPS interference investigation (oscilloscope characterization, shielding, dual GPS restore), lands the repository sync publishing the documentation backlog and the patched baseline parameter files, stands up the task board and the operator onboarding fund, runs formal heat testing, files the marketing discovery deliverable, and distributes the August retro.

**Phase 2** carries the latch and camera V1s to flight ready V2 attachments, decides the attachment interface replacement and the dispenser path, completes the endurance study, integrates QuiverHub onto the Raspberry Pi, flies the first deliberate autonomous Houston mission, and makes the docking station go or no go call from the RTK trough landing test under Javelina Propeller Laboratory.

**Phase 3** publishes dev-kit pricing and an updated bill of materials baseline, runs one external demonstration of the agricultural surveying workflow, stands up a public reliability metrics page, completes the Platform Engineering Report, executes the sales page updates, and expands the flight test campaign with a second operator.

## Commitment Grant Back Pay — July and August

July and August are paid at the rates in force when the work was performed. The team delivered the project's two strongest months while these grants went unpaid.

| Contributor | Monthly | July + August |
| --- | --- | --- |
| Erick | $3,000 | $6,000 |
| Julius | $1,280 | $2,560 |
| Zeynep | $1,280 | $2,560 |
| Alperen | $1,280 | $2,560 |
| KBM | $960 | $1,920 |
| Alex | $960 | $1,920 |
| **Total** | **$8,760** | **$17,520** |

## Retroactive Grants and Flight Campaign (No New Ask)

The July retro distribution (6,000 $ARROW) executed on chain August 31, and the August distribution (6,750 $ARROW, detailed in the August report) follows from the same held reserves, leaving 18,100 $ARROW held. September and October retro will be requested at the roadmap checkpoint, and November at phase close, if the phase record supports them. The 10,000 $ARROW flight test campaign pool carries from April, with payment mechanics finalized in Phase 1 before any draw.

## Roadmap Checkpoint

The October progress report doubles as the roadmap checkpoint: exit criteria reviewed against the record, the September and October retro request, task pool replenishment against delivered work, and any Phase 3 rescoping, with material changes going to the forum before Phase 3 spending continues. Monthly progress reports continue through all three phases, and the next funding request publishes before this one's final phase closes, ending the late funding pattern this proposal corrects.

---

**Approval** allows the transfer of **35,520 USDC** from the Arrow treasury to the Project Quiver multisig to fund operations through November 2026, and authorizes consolidating $6,480.21 of idle bounty allocations into QGB-FLEX with the earmarks above. No new $ARROW transfer is requested. Retroactive grants and the flight test campaign draw from reserves already held on the project multisig.

---

To vote or create proposals from an AI assistant, connect the Snapshot MCP at https://mcp.snapshot.box